Project information
Project Information
The Desk study studied possible hydro power project capacity ranging from 5MW-8.85MW in the river stretch between Khar Khola and Phedi Bazar of Gorkha district near up stream of Daraundi Nadi Dobhan of Majhuwa Deurali village, and identified one site as an optimum to develop a hydro power project of capacity of 8.85MW. This study area lies between 0.50 Km upstream from Daraudi Nadi Dobhan and Khar Khola Dobhan. The Proposed powerhouse lies just 0.80-0.90 Km upstream from Daraudi Nadi Dobhan and intake will be 4.50 km upstream from proposed power house just opposite of Adhaigau of Khar Khola Dobhan of Gorkha district of Duwakot village at right bank.
Studies so far done
- Topographical survey of headworks and power house site in the scale of 1:2000 in February 2020
- Gauge installed in headworks site and power house site in the Daraundi river and read twice daily from November 2020
- Initial Environmental Examination ( on going )
- Geological study at Feasibility level ( on going )
- Detailed Feasibility study level ( on going )